Assign resources to tasks

While assigning resources to tasks is not required to schedule a project in Fusion Online, doing so allows you to:

  • Evaluate the impact of limited resource availability on project timing

  • Analyze resource loading and identify potential overallocation or underutilization

Step 1: Set up the resource sheet

Before you can assign resources to tasks, you must first define the available resources in your project:

  1. Go to the Project Details view.

  2. Click the Resources tab.

  3. Add project resources manually by clicking + create new resource.

You can specify resource names, availability, and other key information. These resources will then be available to assign throughout the project.

Project resources

Step 2: Assign resources to tasks

Once your resource sheet is populated, you can assign resources in two places:

Option 1: Task Details view

  • Open the Task Details view by searching for the task in a task list view or using the global search in the top navigation bar.

  • Select the desired resource(s) and the required number of units.

Option 2: Network Diagram task panel

  • Open the Network Diagram and enter Create Draft mode.

  • Double-click on a task or click the pencil icon to open the task panel on the right.

  • Assign resources just as you would in the Task Details view.

Step 3: Analyze resource load

After assigning resources and rescheduling the project, you can evaluate resource usage in various views:

These views help you assess whether any resource constraints are affecting the schedule.

See also

  • Build the network – Define tasks and logic before assigning resources

  • My Resources – Analyze resource load data for multiple projects

  • Project Details – Access the Resources tab and to create new resources and analyze resource load for the project.